Army Bay WWTP upgrade

  • Client: Rodney District Council
  • Year: 2005

This project covered a major upgrade of the existing site and plant. SKM were responsible for the overall design of the 2 new SBR's and their positioning in the existing system.  Service Engineers took on a design/build role for the complete mechanical component of the job covering; aeration, mixing, pumping, piping and included the electrical works (which was sub contracted to Current Electrical).

 

 

Army Bay WWTP upgrade - Gallery